4M Change Management | How to implement in Manufacturing unit | Template | Format

4M Change Management

4M Change Management| How to implement in Manufacturing unit |Template | Format

Hi Readers! Today here, we are going to discuss 4M Change management related to manufacturing industries with an illustration. You can learn many more things from this article like 4M change concepts, planned and unplanned changes, implementation of concepts in your organization, etc. The concept of 4M change management is generally used to record 4M (man, machine, method & material) related to planned and unplanned changes. This can apply to all internal process changes.

Download the 4M checklist for gap analysis.-4M Checklist-DOWNLOAD

4M Change Management

As we already discussed 4M changes i.e. Man, Machine, Method & Material related planned and unplanned changes. so here, first of all, we have to understand, what planned and unplanned changes are. The plan changes that occur with the advanced information to the pertinent personnel. Similarly, the un-plan change that occurs without prior information to the pertinent person. If once the planned and unplanned changes occurred then a defined action which is mentioned in SOP/Procedure is required to control the occurrence of nonconformity at the shop floor change area.

Illustration / Example (How to implement 4M change management in manufacturing Unit?):

Example of plan change:

Let’s say an organization has planned for preventive maintenance of machine-1 in shift –A, dated xx/1/20xx, and executed the same as per plan. If so then how to record the same 4M change and control the process after PM.

Before implementing 4M change management, personally, I would recommend that try to prepare the procedure /SOP as per your organization’s nature of production, like the 4M procedure, change tracking record, list of trained operators, list of machines, material list, etc.

According to the above example scenario, we are going to record the 4M change in the below template (this template is only for reference)
DateMachineShiftType of changeDetails of changeAction taken
xx/1/20xxmachine-1APlanned / machinePreventive maintenanceSet up approval checking

 In this way, you can maintain the change record. For your better understanding and more clarification, we have given below another example related to the unplanned 4M change.

Example of un-plan change:

 For example, an operator on leave without prior information to the pertinent supervisor and you as a supervisor planned for running the machine-1 with the help of other operators. In that scenario, how to record the 4M change, and what action is to be taken?

Similarly, we are going to record the un-plan change as per the above 4M change template or format.

DateMachineShiftType of changeDetails of changeAction taken
xx/1/20xxmachine-1AUn-planned /ManThe operator is on leave without intimationA similar skilled operator will run the machine/machine setup approval to be done

The 4M change record can be helpful for analysis in the future if there will be any issues with the product. And the action you have taken at the time of the 4M change can control the process as proactively.

I hope the above example is meaningful for your better learning and understanding related to 4m change management implementation in your organization.

Example of Abnormality ( Abnormal situation handling):

It is very important to understand all three situations/changes i.e. [1] plan change, [2] un-plan change, [3] abnormality. now here we are going to discuss the 4M change management of abnormal situation handling (abnormality). Suppose in a production line, a machine-1 on a sudden breakdown, for this situation we are going to record the 4M change, and the same is given below.

DateMachineShiftType of changeDetails of changeAction taken
dd/mm/yymachine-1B-shiftAbnormality /MachineMachine-1 on sudden breakdown1) Run a backup machine, if available.
2) Do the setup approval & Retroactive inspection
3) Containment action.

Free Templates / Formats of QM: we have published some free templates or formats related to Quality Management with manufacturing / industrial practical examples for better understanding and learning. if you have not yet read these free template articles/posts then, you could visit our “Template/Format” section. Thanks for reading…keep visiting techiequality.com

Useful Post:

C Chart Excel Template | Formula | Example | Calculation

P Chart Excel Template | Formula |Example |Control Chart | Calculation

Variation Calculation in Excel | Types of Variation |Manufacturing Example

Equipment Ranking Process | A B C Ranking of Machine with Manufacturing Example

More on TECHIEQUALITY

4M Checklist Template | Free Download Format

4M Checklist Template

 4M Checklist Template |Free Download Format:

Hi Readers! Today we will discuss here on 4M Checklist Template. Generally, the 4M concept is used in several methodologies, In the Cause and effect diagram it represents the potential causes and similarly, it is also used as a checklist for Kaizen. In the kaizen approach, there are some checklists used as [1] 5MUs checklist [2] 5W1H checklist [3] 4M Checklist. But here we will only explain on the 4M checklist. We have prepared the 4M checklist for your ready reference. You can easily download this checklist/check sheet from the below link.

DOWNLOAD-4M Checklist/Check-sheet / 4m analysis template excel

Sample 4M Checklist Copy:

4M Checklist Template
4M Checklist Template:

4M i.e. Men, Machines, Materials & Methods are the common aspects and important for quality improvement and KAIZEN. Questions to be asked related to 4M to implement kaizen activities effectively are;

Man (Workforce)
Is he responsible?
Is he accountable?
Is he qualified?
Is he experienced?
Is he assigned to the right job?
Is everything in a good working order?
Does he follow standards?
Is his work efficiency acceptable?
Is he willing to improve?
Machine
Does it meet process capabilities?
Is the oiling/greasing adequate?
Does it meet production requirements?
Does it meet precision requirements?
Does it make any unusual noise?
Is the layout adequate?
Are there enough resources available?
Are there any mistakes in the material grade?
Is PM done as per plan?
Material
Is there any issue with material flow?
Are there any impurities mixed in?
Are there any mistakes in quantity?
Is the inventory level adequate?
Is there any wastage of materials?
Is the material quality standard adequate?
IS it a method that ensures a good product?
Method
Is the SOP adequate?
Is the SOP available on the shop floor?
Is the SOP upgraded?
Is it a safe method?
Is the setup adequate?
Is it a safe method?
Is it an efficient method?
Is the sequence of work adequate?
Are there any mistakes in the material grade?
Are the process characteristics set as per standard?
Are the product characteristics meeting the standard requirement?
Template
Example: We had audited the manufacturing process and got the below observations;
4M Checklist Template
4M Checklist Template

During the process audit through the 4M checklist, we have observed so many improvement points, these are mentioned in the above checklist remark column. In this way, you can easily find out the process improvement points. Download the above 4M Checklist and try to customize it according to your manufacturing process.

How to Implement the 4M checklist /Check sheet in Manufacturing Industries?

I always try to share my own industrial experience so that my readers can easily understand, learn, and implement the skill-based concept in their operational process.

Posts/articles on this website are skilled base, you can read our articles for your personal learning, for training purposes, and for practical implementation in the industry as well.

Generally, we use the 4M, and 6M check sheets to audit /investigate and to check the condition and lacking points of 4M factors (Men, Machine, Method, and Material). Some industries plan the checking schedule on a weekly and some on a monthly basis as per the production plan. By doing so we can easily maintain the machine condition, reduce the B/D, Increase the machine run time, we can identify the on-job training of operators /workers, maintain the material inventory, monitor the effectiveness of the Method, we can further improve our process, etc.

Below are the steps for implementation of 4M checklist/ check sheet:
  • Prepare the 4M checklist /Check sheet as per your Process in detail considering with past 6 months’ quality defect causes, B/D nature causes, customer complaints, etc.
  • Define the Checking plan (e.g. weekly, monthly, etc.)
  • Check 4M factors by using the 4M check sheet as per your plan,
  • Write the observations.
  • Discuss with the concerned department and formulate the Action plan / CAPA.
  • Implement the CAPA /Action Plan.
  • Monitor the implementation of the action plan (For example, verify it in the next checking).
4M Change Management:

After doing the 4M Audit you can easily identify the 4M-related changes. the above 4m checklists is mentioned for your reference but the checking points are not limited. you can customize the above checklist as per your manufacturing process.

You can identify and monitor the 4M changes in the 4M change Record sheet as per below.

Sl. No.ProcessType of ChangeNature of ChangeDetails of ChangeAction TakenSet-up ApprovalRetroactive checkContainment Action
4M Change record

Example:

Type of Change: Man, Machine, Method, and Material.

Nature of Change: Plan change, Unplan change, Abnormal change

FAQ (Frequently Asked Question):
What is 4M in Manufacturing Industries?

Ans.: In Industries the term 4M is generally used as [1] Man [2] Machine [3] Material & [4] Method.

What is 4M method?

Ans.: The 4M method is generally used in manufacturing industries for problem-solving /analysis. These terms are generally represented in 4M change management and also in the Cause and effect diagram or Fishbone diagram. The potential causes are basically represented under the category of 4M- Cause and effect diagram for further processing like causes/problem analysis and validation of causes, etc.